Electricity
The power line from the road to the transformer box, a distance of over 300', was installed by boring horizontally at 4' below grade and below all the tree roots. By installing the electric line underground, especially in our heavily forested area, we did not have to cut any existing trees, nor do we have to be concerned about trees falling on the wires. We also eliminated the use of toxic treated power poles
|
 

Fri. 10:00am -- Digging thru the frost to bury
the electric line from the transformer to the meter on the dome. The line
is being inserted in Schedule 80 plastic pipe.
 
Mon. -- Wiring the meter hub.
 
Mon. -- Wiring the 200 amp panel box and
installing circuit breakers.

Tues. -- To install the 8' copper ground rod, we
had to drill thru 12" of frost.
 
 
Tues. -- The electric line is being installed by
going down 4' to get below the frost line. They then
have to bore 350'
horizontally under the pine forest to the transformer pad.
 
Thurs. 3:15pm -- Finally we can get rid of the
8000 watt generator at $15.00/day gas consumption. The power
company came
yesterday and connected us to the grid. |
 |

37955 Bridge Rd., North Branch, Minnesota 55056 USA
Just 45 minutes north of the
Minneapolis/St. Paul metro area.
View A Google Map
|
|
Minneapolis/St. Paul Area: 651-674-4292
Within the United StatesToll-Free: 800-733-7107
Fax: 651-674-5005
International Phone: 01-651-674-4292
International Fax: 01-651-674-5005
Email: nsd@naturalspacesdomes.com
Twitter: http://twitter.com/nsdomes
Facebook: Click here
Skype: Naturalspacesdomes
|
Office Hours: 8:30 - 5:00 p.m. Monday - Friday
Weekends: Appointment Only |
|